Inside a $30M Hotel Conversion: Rewiring for Two Hilton Brands

Klamath Falls, a 1996 Shilo, now being pulled apart into a Homewood Suites and a Hampton under one roof. 148 rooms. 98,000 square feet. A $30 million budget, Greens developing it with USDA rural-development money. First extended-stay lodging in that city. We're on the common and public side. This is not a carpet job, and it isn't ground-up either. The electrical work is whatever the 1996 building will actually allow.

Architectural elevation sheet for the Homewood Suites and Hampton by Hilton dual-brand conversionCommercial

Two brand standards, one thirty-year-old building

Two Hilton flags, one service. Lighting levels, how many receptacles the guest can see, sign power, the breakfast kitchen. All of that lands on the same corridors and the same back-of-house. You don't get a second utility because the brands don't match.

The 1996 distribution was sized for a Shilo. Room by room we decide what stays, what gets a new feeder, and what comes out. Ceilings open. Slab gets cut where the new layout wants a circuit the old hotel never had.

Where the electrical scope concentrates

Guestrooms are the obvious scope. The heavy electrical is the public side. The kitchen and buffet are a restaurant stuffed into the hotel: equipment circuits, hood, refrigeration, finish lights. The lobby has to read as two brands at once. Corridors carry new power and life-safety through a building people are still walking.

  • Power distribution and branch circuitry rebuilt through remodeled spaces
  • Lighting and controls to current energy code and brand spec
  • Commercial kitchen, buffet, and dining electrical
  • Lobby, corridor, and common-area systems
  • Receptacles and equipment connections throughout
  • Continuous sequencing with the GC and every other trade in the same spaces

Backup power and life safety in hotels

Yes, hotels keep something alive when the utility dies. Egress lights, exit signs, fire alarm. Batteries, an inverter, or a generator, depending on the building. Bigger extended-stay places often put elevators and refrigeration on the generator too. A dark hotel full of people is an evacuation, not an inconvenience.

Do that layer while the ceilings are open. Testing egress lighting across 98,000 square feet is miserable after the hard lid goes back.

Why conversions are their own discipline

Ground-up obeys the drawings. A conversion obeys the drawings until demo opens a wall. Then the feeder isn't where 1996 said it was, the structure blocks the route, and three trades want the same corridor. Our job is to absorb that without sliding the date.

Decisions happen at the gear, the same day. A week of RFIs is how these jobs miss the opening.

Common questions

Do hotels have backup generators?
Life-safety systems (egress lighting, exit signs, fire alarm) must stay powered during an outage, and hotels meet that with battery systems or standby generators depending on size. Many full-service and extended-stay properties also back up elevators, refrigeration, and select guest services. We size, install, and maintain commercial standby systems including automatic transfer switches and load management.
What does the electrical scope of a hotel renovation include?
Typically power distribution and branch circuit rework, lighting and controls to brand and energy-code standards, commercial kitchen and dining electrical, corridor and common-area systems, life-safety lighting, and low-voltage pathways: sequenced with the GC so spaces hand over on schedule.
Can a hotel stay open during an electrical renovation?
Phased renovations often keep wings open while others are rebuilt: work is sequenced by floor or wing with temporary power and protected egress. Full conversions like a brand change are usually done closed, which lets every trade move faster and the building reopen to a higher standard.
Do you work on hotel projects outside the Portland metro?
Yes. We serve all of Oregon (this project is in Klamath Falls) and we take on select larger projects in Idaho.
Who decides which old circuits stay?
Field call, with the GC, cover off. If the old feeder has ampacity and a legal path, it stays. If the kitchen won't live on it, it goes. We write that down before anyone leaves. Not three weeks later as a surprise.
What should be in hand before the electrical bid?
This property's brand requirements. The architectural set. The kitchen cut sheets if they exist. Sister flags do not ask for the same plug counts. The corporate PDF is the wrong book.
Written by the licensed electricians at Paramount Electric Co. (OR CCB #195783 · ELEC C818) and reviewed by Maurice Greven, Project Manager / Supervisor, who holds Oregon supervising electrician license #4828S. Have a job this applies to? Call (971) 471-7897 or request service online.

Planning a hotel renovation or brand conversion?

Send plans and a scope for a complete electrical bid, or call (971) 471-7897 to talk through the project.